Emergency construction of the proclaimed road DR4103 from Okatana to Epyeshona to Amutanga (Phase 1) over a distance of 6.8 km.

The project involves the construction of gravel roads, including the removal and reconstruction of road surfaces.

Project Type :

Status :

Location : 

Client :

Contract Value :

Scope:

Roads

OTESA – Main contractor

Okatana Constituency

Roads Authority of Namibia

N$ 10 Million

Construction of gravel roads.

Screen Shot 2023-09-13 at 10.26.58 AM.png
Screen Shot 2023-09-13 at 10.26.58 AM.png
Screen Shot 2023-09-13 at 10.26.58 AM.png

Project consists of two phases

All two phases are located between MR120 road and Omungwelume road.

Scope of work covers

  • Construction of fill layers: Processing of fill layers in 300mm layers and to be compacted to 90% modified AASHTO densities.

  • Construction of SSG layer: Importation of G7 to be processed in 150mm layers and to be compacted to 95% modified AASHTO densities.

  • Construction of Wearing course: Importation of G5/G6 to be processed in 150 mm and to be compacted to 98% of Modified AASHTO density

  • The width of the road is 7.5m with a side slope of 1:2 and fixed toe at 2.9m.

  • Drainage, service ducts, culverts, stone pitching will be done in phase1 and phase2.